Month |
Percentage |
|
Note |
|
Apr 07/08 |
56.00% |
|
|
|
May 07/08 |
53.00% |
|
|
|
Jun 07/08 |
49.00% |
|
|
|
Jul 07/08 |
51.00% |
|
|
|
Aug 07/08 |
49.00% |
|
|
|
Sep 07/08 |
55.00% |
|
|
|
Oct 07/08 |
54.00% |
|
|
|
Nov 07/08 |
52.00% |
|
|
|
Dec 07/08 |
55.00% |
|
|
|
Jan 07/08 |
53.00% |
|
|
|
Feb 07/08 |
52.00% |
|
|
|
Mar 07/08 |
55.00% |
|
|
|
Apr 08/09 |
52.00% |
|
|
|
May 08/09 |
45.00% |
|
|
|
Jun 08/09 |
41.00% |
|
|
|
Jul 08/09 |
41.00% |
|
|
|
Aug 08/09 |
42.00% |
|
|
|
Sep 08/09 |
42.00% |
|
|
|
Oct 08/09 |
41.00% |
|
|
|
Nov 08/09 |
45.00% |
|
62% for month of November |
|
Dec 08/09 |
45.00% |
|
50% for month of December |
|
Jan 08/09 |
45.00% |
|
|
|
Feb 08/09 |
44.00% |
|
|
|
Mar 08/09 |
41.00% |
|
|
|
Apr 09/10 |
37.00% |
|
Issues with delay in work invoices being paid adveresly affecting indicator |
|
May 09/10 |
34.00% |
|
Issues with delay in work invoices being paid adveresly affecting indicator |
|
Jun 09/10 |
33.00% |
|
Issues with delay in work invoices being paid adveresly affecting indicator |
|
Jul 09/10 |
30.00% |
|
Issues with delay in work invoices being paid adveresly affecting indicator |
|
Aug 09/10 |
33.00% |
|
Issues with delay in work invoices being paid adveresly affecting indicator.Est fugure for Aug 09. |
|
Sep 09/10 |
35.00% |
|
Issues with delay in work invoices being paid adveresly affecting indicator |
|
Oct 09/10 |
24.00% |
|
Planned expenditure curtailed due to spend pressures on reactive maintenance budgets |
|
Nov 09/10 |
25.00% |
|
Planned expenditure curtailed due to spend pressures on reactive maintenance budgets |
|
Dec 09/10 |
37.00% |
|
Planned expenditure curtailed due to spend pressures on reactive maintenance budgets |
|
Jan 09/10 |
27.00% |
|
Planned expenditure curtailed due to spend pressures on reactive maintenance budgets |
|
Feb 09/10 |
27.00% |
|
Planned expenditure curtailed due to spend pressures on reactive maintenance budgets |
|
Mar 09/10 |
27.00% |
|
|