User Screen "Introduction & Framework"User Screen "Portfolio Holders"User Screen "Strategic Performance Report "User Screen "Key Local Indicators Report"User Screen "Community Plan"User Screen "Corporate Plan and Delivery Plan"User Screen "Plans,Policies and Strategies"User Screen "Indicators On/Above Target"User Screen "Indicators Below Target"Published onThursday, 26th April 2012Show Indicator "HLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)" using Object Form "Details"Show Indicator "HLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)" using Object Form "Links"Show Indicator "HLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)" using Object Form "Printable"Show Indicator "HLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)" using Object Form "Update"Show Indicator "HLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)" using Object Form "Edit"User Screen "Our Performance"Picture showing Z:\NBBC-logo-09_ASSET_WEB.gifHLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)
Person "Performance and Quality Manager"User Screen "Introduction & Framework"User Screen "Portfolio Holders"User Screen "Strategic Performance Report "User Screen "Key Local Indicators Report"User Screen "Community Plan"User Screen "Corporate Plan and Delivery Plan"User Screen "Plans,Policies and Strategies"User Screen "Indicators On/Above Target"User Screen "Indicators Below Target"User Screen "Our Performance"
Table showing Hierarchical Self of Object Form "Performance"Indicator "HLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)"Indicator "HLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)"Table showing Hierarchical Self of Indicator "HLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)"Chart showing Indicator "HLPI 4 - a. Waiting Time For Adaptations (approval of grant/assistance)"Below TargetOn TargetAbove Target

Month

Value

Note

Apr 07/08

35.7

   

   

May 07/08

48.5

   

   

Jun 07/08

53.0

   

   

Jul 07/08

49.8

   

   

Aug 07/08

53.2

   

   

Sep 07/08

46.8

   

   

Oct 07/08

53.0

   

   

Nov 07/08

46.4

   

   

Dec 07/08

56.0

   

   

Jan 07/08

53.4

   

   

Feb 07/08

43.6

   

   

Mar 07/08

43.0

   

   

Apr 08/09

39.2

   

Actual is 39.2.Please note that all Housing indicator tolerances were amended for 2008-09 so that indicators can only be on target if the target is met(this change was made in Sept.2008).

May 08/09

45.0

   

   

Jun 08/09

50.0

   

   

Jul 08/09

29.4

   

   

Aug 08/09

39.2

   

   

Sep 08/09

30.6

   

   

Oct 08/09

37.4

   

   

Nov 08/09

37.8

   

   

Dec 08/09

38.8

   

   

Jan 08/09

39.8

   

   

Feb 08/09

39.4

   

   

Mar 08/09

40.4

   

   

Apr 09/10

30.6

   

   

May 09/10

36.2

   

   

Jun 09/10

38.2

   

   

Jul 09/10

41.2

   

   

Aug 09/10

42.0

   

   

Sep 09/10

41.4

   

   

Oct 09/10

42.6

   

   

Nov 09/10

42.8

   

   

Dec 09/10

42.4

   

   

Jan 09/10

41.4

   

   

Feb 09/10

41.4

   

   

Mar 09/10

41.2

   

   

Apr 10/11

31.6

   

   

May 10/11

32.8

   

Team target introduced and monitored weekly.

Jun 10/11

34.8

   

Progressing above target

Jul 10/11

34.0

   

Presently progressing above target.

Aug 10/11

34.2

   

See adjacent indicator for comment.

Sep 10/11

34.2

   

Total of 69 approvals so far this year.  Currently 28 applications pending plus 55 enquiries waiting to proceed.

Oct 10/11

34.4

   

The current budget is committed in regard to the scheduled scheme (32) and current approvals (40).  Current enquiries = 23.

Nov 10/11

34.0

   

Waiting times may increase due to budget commitments.  Current enquiries = 18.

Dec 10/11

35.0

   

All money for 2010/11 has been allocated therefore expect waiting times to increase over the next few months.

Jan 10/11

34.6

   

Awaiting new budgets.

Feb 10/11

34.6

   

Awaiting new budgets.

Mar 10/11

34.6

   

Grants being processed - within target.

Apr 11/12

   

   

Awaiting for 2011 / 12 funding

May 11/12

   

   

Affected by wait for funding

Jun 11/12

   

   

   

Jul 11/12

   

   

   

Aug 11/12

   

   

   

Sep 11/12

   

   

   

Oct 11/12

   

   

   

Nov 11/12

   

   

   

Dec 11/12

   

   

   

Jan 11/12

   

   

   

Feb 11/12

   

   

   

Mar 11/12